Traffic in the Hicksville, Ohio area
ODOT CONSTRUCTION PROJECTS
Summer/Fall 2006
The latest traffic information for Defiance, Williams, Fulton, Henry, Putnam or Paulding counties.
Defiance, Ohio SR 24
Start date: 5/15/2006 8 AM
Estimated end date: 10/31/2008 4 PM
Traffic on U.S. 24 maintained at all times during reconstruction of the existing highway lanes and
construction of two additional lanes to expand the route to a four-lane highway from SR 424 to just
east of the SR 15/18 interchange. The four-lane section from SR 15 to SR 66 is currently reduced to
one lane in each direction. Occasional one-lane closures are occurring as needed.
Bryan, Ohio SR 2/SR 34
Start date: 9/18/2006 7 AM
Estimated end date: 10/28/2006 6 PM
SR 2/SR 34 at Huntington Drive in Bryan, OH will be closed starting Monday, September 18, 2006 for 40 days (weather permitting) to replace a culvert.
Detour: SR 191; US 6; SR 15
See map
Henry County, Ohio SR 65 south of McClure
Start date: 8/29/2006 6 AM
Estimated end date: 11/15/2006 7 PM
SR 65 is closed in two locations for the replacement of existing concrete slab top bridges over two separate
drainage areas (both located south of McClure between County Roads G and H) including approach reconstruction.
The project completion date is early-November, 2006 (weather permitting).
Detour: US 6; SR 109; SR 18
See map
Hamler, Ohio (Henry County) SR 109
Start date: 9/11/2006 7 AM
Estimated end date: 9/21/2006 6 PM
CSX Railroad has closed SR 109 at Baltimore Street in Hamler, OH until approximately September 21
(weather permitting) to rebuild the CSX railroad crossing.
Detour: SR 18; SR 109; SR 613
See map